Articles tagged as: I-69 Development Partners
August 1, 2017
State Still Finalizing Takeover Of I-69 Section 5
The state reached an agreement last month with private developer I-69 Development Partners and its bondholders to take over construction of Section 5.
Read MoreJune 29, 2017
IFA Approves State Takeover Of I-69 Section 5
The action finalizes an agreement the state announced two weeks ago. Under the arrangement, the IFA will reimburse the developer's bondholders for $246 million and the Indiana Department of Transportation will take the project over by the end of July.
Read MoreJune 16, 2017
State Reaches Agreement To Take Control Of I-69 Section 5
INDOT will assume primary control of Section 5 construction, between Bloomington and Martinsville, by the end of July.
Read MoreSeptember 7, 2016
I-69 Developer Owes Subcontractors More Than $9 Million
Bloomington's mayor says at least one subcontractor walked off the job Friday because of an ongoing pay dispute.
Read MoreSeptember 7, 2016
The Latest: Pence's Office Defends Actions On I-69 Project
Indiana Gov. Mike Pence's office says the state is holding a private developer accountable following a work stoppage on the Interstate 69 extension project.
Read More